A six month work placement at Finley as part of his civil engineering
degree first brought Jim Todd to the district and introduced him
to irrigation. Originally from Murwillumbah, NSW, he joined the Water
Conservation and Irrigation Commission in 1950 after graduating,
and moved to Deniliquin to assist with the construction of the new
system, and later became the District Engineer.
INTERVIEW TRANSCRIPT
The following text is based on an edited transcript of an interview
recorded with Mr James Todd in March 2005.
Key topics: Gazetting of irrigation districts, construction of Stevens
Weir, relief work, dragline excavators, Box Creek, clearing, drainage,
horse teams, plant, Mulwala Canal, Lawson syphons, official opening
of syphons, farm development and water use, migrant workers, flooding.
After World War I there was a lot of soldier settlement right
through this area which, in the ensuing depression of the 1920s was
in a very serious condition. In fact a great many of the soldier
settlers south of the town of Deniliquin literally had to walk off
their blocks. It was a combination [of lack of money and drought],
but it simply wasn't - a living wasn't there. When
I first arrived in Deniliquin, going out the Barham Road here and
there and you could see a small clump of pepper trees and a small
heap of bricks. This is where somebody had attempted to establish
a farm.
A different plan
The decision was made by the New South Wales government to establish
irrigation through this area and a part of the reason for this was
to provide relief for these farmers who were having a very hard time.
The Water Commission already had irrigation areas on the Murrumbidgee,
but in this stage in the irrigation areas they resumed all the land,
divided it into farms and allocated them with assured water rights
and so on. But for this area they changed the plan to what they called
irrigation districts in which the proposal was to supply water to
each existing property in the area selected. On the MIA they
provided drainage on the Murray here, expecting relatively small
scale irrigation development. They deemed it not necessary
to provide drainage. It was expected that water would be used
primarily to grow pastures to supplement their essentially dryland
development. That was the original plan.
They weren't resuming the ground, so they had to have permission
from the landholders, not individually but they'd declare a
certain district, such as the Berriquin or the Deniboota or the Denimein
irrigation district, and it would be advertised, and people could
object to it. If a significant proportion of the landholders
objected to it, it would go before a locally constituted Land Board.
In the Wakool district it wasn't necessary, there were insufficient
objections and they went ahead with it, and that work started in
1932, I think it. But there were sufficient objections in the Berriquin
district, which was promulgated at the same time, and that had to
go before a Land Board. Basically people didn't want to change
what they were doing and were afraid of the costs. But that's
my supposition of it. The locally constituted Land Board did
uphold the constitution of the Berriquin district, but that meant
it was about two years later than the Wakool district in the construction
of the work.
Weir provides relief work
The first work for the Wakool district was the Stevens
Weir. This was in the depression and the resident
engineer for the Stevens Weir was brought down from MIA. The
job was there to employ the local unemployed, and it was
done largely on relief work, certainly initially, with
typically men working two weeks on and one week off on
relief work, to share the benefit around. The excavation
of the Wakool main canal initially was done by a steam
powered dragline. It travelled on rails, not on tracks. They
laid rails ahead of it.
The story is told that every morning - Steve Whetham was the engineer,
he used to step outside his field office, at 9 o'clock and
sack two men. All they had to do was be there. He took
care to not sack any of the key men. And he'd quite happily
put them on again a fortnight later. It was a very crude but
widely used disciplinary measure to keep the people on their toes.
At the same time when branch channel construction was going on, it
was quite typical for a gang of men to be working out on the channel
site and two or three men sitting in the shade. They were waiting
for the ganger to sack somebody. There was no shame in it. The
sewage works in Deniliquin were put in at about the same time on
the same basis, and I remember one of our workmen saying, "I
had the honour of being sacked in my own backyard". But
that was the way it was done.
The New South Wales Government, they planned the whole thing out
and their intention was to develop irrigation right across what is
now the Berriquin district, an extension to its north, which is now
incorporated in it, which was called the Jenargo irrigation district
and to the west, the Denimein irrigation district, with a rather
indefinite western boundary. They called it Denimein, being
an abbreviation of Deniliquin and Moulamein; and the Deniboota, which
was a corruption of Deniliquin and Womboota - Womboota being a reasonably
established locality south of where Bunnaloo is now. At that
stage I don't think they'd very firmly fixed the limits. In
fact I know they hadn't because they've been extended
since.
Plant imported from U.S.
Now they purchased this heavy plant from America, and
the star of it was the four Bucyrus excavators. They
have always carried the name plate of Bucyrus-Erie, but
they never were Bucyrus-Erie, they were Bucyrus-Ruston
because of the existence at that time of empire preference
on your imports. And to satisfy that, the Erie motors
were replaced by a Ruston engine in each of these machines,
so they were always effectively Bucyrus-Ruston, and that
was the reason for this slightly strange shape of the cabin
on those excavators.
Initially the top levels of the excavation were done by horse
teams with scoops, but that was quickly stopped and the horse teams
moved into the branch channel construction and the Bucyrus drag-lines
were just doing the whole of the excavation. These machines
were big. They had either the choice of a 3 yard bucket with
a - I think was a 40 foot jib - or a 4 yard bucket with a 40 foot
jib or a 3 yard bucket or a 4 yard bucket with a 50 foot jib. It
was just simply an extension of jib. In my time we never used
the extension and only used the 3 yard buckets when we had to do
some repair work on one of the 4 cubic yard buckets. These
machines were 22 foot wide and weighed 120 tons, and it was always
planned to take them across the Edward River.
So, as the work approached the Edward River, they had to build
a bridge across the Edward River to carry these draglines. It
was a very heavily built bridge, much heavier than the actual syphon
construction needed but it had to get these machines back and forwards
across the river. That bridge has only in recent years been
totally demolished, but I suppose for the last 30 years it was rather
derelict.
Now, as the[ Mulwala Canal] was built, a telephone line was built
along with it, and for quite a long distance a pipeline was laid
to keep water up to the camps and the excavating plant and there
was a pump at Mulwala pumping from the weir - pumping from the river
there, pumping along the work. As water came along, of course, I
think they simply stopped pumping water out, but the telephone line
was laid right from Mulwala through to Deniliquin. It was all double
line, but with connections to the Finley office. This was for passing
the information about construction and later channel operation.
Early development slow
Water first came to the first part of the Berriquin
district in 1938, but then there were the intervening war
years, and after that there were prosperous years during
which the development of the irrigation was relatively
slow. The existing farmers who had survived the depression
didn't have to extend themselves terribly to make
a good living without much irrigation in the immediate
post-war years because the prices were very good then.
There was a lot of war service land - war service subdivisions
going on at this time. Soldier settlement was the general term. And
the development - corresponding development across the border in
Victoria was probably about 10 years ahead of New South Wales, so
there was a fairly steady migration of Victorian farmers to the cheaper
land and good water supply on the north side of the river. That
introduced a good deal of encouragement for people to look over the
fence and see how it was done.
I was appointed down here to the Deniboota [and Denimein] construction
in 1950 and my work was in the branch channel construction, which
was at that stage going ahead in Denimein. The Deniboota couldn't
start until the syphon was complete, but there was a lot of other
extension of channels going on to serve the soldier settlement subdivisions
and private subdivisions and it was gathering pace. So there was
quite a lot of construction work going on within the irrigation district. Escape for surplus water
The draglines had completed the excavation of Mulwala
Canal to the proposed junction with the Wakool Main Channel,
and Deniboota Canal to a point close to Bunnaloo. They
had been excavating the enlargement of the Wakool main
and extension of it from the Mulwala Canal. At that stage
the channel was getting rather too small to use the draglines.
But they had the machines and the decision was made
to excavate the Box Creek escape channel. We had to do
a lot of clearing for the draglines, particularly along
Box Creek because there was standing timber most of the
way. The trees in the forest in Box Creek were almost entirely
Black Box, which was useful only as firewood; there was
no logs in them.
Now Box Creek is a major drain, but because the
constitution of the irrigation district said we did not
provide drainage, it was called an escape channel and was
connected to the end of all the branch channels to get
rid of surplus water, because it had been realised by the
irrigation authorities that drainage was inevitable.
With the increasing development, you had to be able to get rid
of surplus water. In the original concept it was expected that
these irrigation district farmers would only develop a relatively
small amount of irrigation to provide a reserve of fodder to withstand
dry times. That was the theory. It didn't work
out because what the farmers - as they started to develop, they found
that there was money in this.
The excavation of the branch channels was almost entirely by horse
teams, with eight-horse or 10-horse teams. There was one contractor
who was using a Crawler tractor - an International TD9 40 horsepower
with a scoop. He didn't do anywhere near as nice a job
as the horses did. Nobody was using bulldozers for excavating
channels. You could use a bulldozer to dig a site out for building
some structure, but it wasn't suitable for digging channels
at that stage of the technology.
That went on until about '57 or thereabouts when the small
bulldozers were taking over. Then it was decided to build the Deniboota
Escape. Before that with the horse teams and the small tractors we
were letting earthwork contracts and about 20,000 cubic yard - 25,000
cubic yard batches, which would be three or four months work for
a horse team. But when we started in Deniboota, we decided
to allow a big contract - bigger contracts, I think 120,000 to 150,000
cubic yards because it would attract a lot more tenders, which it
did.
Assisting at the syphons
I was on the branch channel work and I spent about
one year off it and I was taken off that at a slack time
to supervise the clay lining of a section of the Mulwala
canal between Aljoes Syphon and the Edward River, because
you have to realise that that section in particular was
all underlined by sand. We didn't get down
to sand in the excavation but it's not far down till
you're in sand all through there because it's
on an ancestral Murray stream.
And for that we were supplied with two little excavators, Tournapul
Scoops - horrible things. They were very effective but they
were most dangerous looking things. It was just a two-wheeled
tractor couple onto a scoop with hydraulic controls between. And
I remember the foreman saying, "You need to be certifiable
to drive one of these". And they used to drive them pretty
furiously. But they were hauling clay off the bank downstream
of the Four Post Road, put into there, and it all had to be rolled
and compacted in.
And as that was completed, I was assisting for a while on the
Lawson Syphon work.
At that stage Eric Nicholas was the resident engineer
at Deniliquin and Tony Vidal was in charge of the work
actually on the site of the Lawson Syphon. At that
stage the syphon field office had shifted to the north
bank of the river. The initial work always - the
first job was to coffer-dam off half of the river with
steel sheet piling and to pour a junction block in the
middle of the syphon where the two halves of the syphon
were joined together. It's all under the ground,
but that was the first job.
Syphons help stabilise town, farming
[The Lawson Syphons] was very important locally because it maintained
employment in the area at a time when the irrigation farming was
getting underway really, and so that it filled in a gap from the
depression through to the intense farming development, which is Deniliquin
really.
The Lawson Syphon construction at the time was the largest steel
sheet pylon job in the southern hemisphere, so it was significant
that way. The piles were driven and extracted with steam hammers. It
was about the end of that time that they started using big air compressors
to do the same thing, with the same hammer, the air compressors. Much
easier to manage. But these days they generally use a diesel
hammer.
The initial thought with the irrigation all up and down here was
a small amount of irrigation to grow fodder to stabilise the failing
dryland farming within this district. Now, that was the initial
concept. The widespread irrigation - rice growing was already
underway up on the MIA, but there was no thought of any such thing
down here. Rice growing down here got underway using Italian
prisoners of war on the Tullakool farm which, at the end of the war
- after the end of the war was - became the Tullakool irrigation
area, with drainage, etcetera, for intense development. But
that wasn't the original plan. It was a wartime exigency
to grow rice to feed the people who would normally have got their
rice from Thailand.
Prepared to work hard
The Italian immigrants were coming to Australia, and
the only English they'd learnt, which was on the
boat coming out. They'd run classes on the
boat but very limited ability, and they had very limited
English. And Ron Butcher was the foreman out at the
syphon. They'd put in a camp out at the syphon,
and they'd line this fresh batch up and ask them
their names. And the names meant nothing to Ron,
so he'd name them - Tom, Joe, Harry. And it's
surprising how those names stuck. The leading hand pile
driver was Charlie – Dandrea was the surname. Ron
Butcher didn't know that Giuseppe was equivalent
to Bill - he didn't know that, but it was Charlie. We
always knew him as Charlie Dandrea. The name stuck. He
was built like a gorilla, and I always reckoned if the
pile driver failed, he'd take a 14 pound hammer and
do the job."
"But that was the sort of attitude; most of them were really
eager, because they came out here to better themselves - with nothing
- and they were prepared to work hard to do it, and most of them
did. One of the odd ones that I named I reckoned he
was an artist with a bulldozer; he never really learned English,
and I know he had a wife and a couple of daughters in Italy. I don't
know whether he ever got them out. He should have. He
was a bloke you'd have liked to have helped but he was pretty
helpless unless he was up on the bulldozer. I asked him where
he learned to drive a bulldozer, and he said, "Driving tanks
in the Italian Army".
"It was very tough for the foreign - the new Australians,
as we used to call them. I'm glad that Caldwell (Caldwell
was then the Minister for Immigration) coined that phrase "new
Australians" because, you know, they got a lot of bad names
too, but we eventually adopted the term, and we had a lot of them
out at the syphon."
Opening of the Lawson Syphons
The opening ceremony had to be held on the outlet because that
was the only place where you could accommodate a large number of
people, so they built a rostrum - a sheltered rostrum on the outlet
works, and the multitude lined up along there. The access road
went down the western side, so most of the people were on the western
side. Quite a few people on the eastern side - but they had
to walk around to get to that.
To officially open her of course they had to run water through,
and there was probably about 8 or 10 seconds delay from when they
started winding the winch handles before the water would turn up
at the bottom, so they must have had have worded the Premier to give
them [time] in the office to signal the blokes to start winding handles,
because no sooner they declared it open, and the water welled up
and flowed down the channel. And every kid on the bank threw
a clod in, as you can just picture them doing, because there was
all clods. It was all fresh earthworks, so there was all clods.
But what I do remember about it was - I think it was rather shameful. -
it was called the Lawson Syphons. It was insisted that it wasn't
named after Joe Lawson, the local member of Parliament, Country Party. Nobody
ever believed that, because there was a Labor government in power
at the time - for quite a long time at the time, and it was officially
opened by the Labor Premier. And after all the speechifying
and the Premier (Premier Cahill) officially opened it, he said, "I
now invite Joe Lawson to say a few words". By this time
everybody had turned around and was walking away. And you could
have foreseen it happening. I'm not sure it wasn't
done deliberately."
The workshops were all on the southern side of the whole - the
southern side of Aljoes Creek, because that was flood-free. And
the camp - the camp similarly was on that side because that was flood-free. Everything
between there and the river was liable to flooding. Any minor flooding
would flood the syphon works out, as it did very frequently. The
Aljoes Creek syphon was built during the times when the work on the
syphon under the Edward River was interrupted by minor flooding.
There seemed to be one about every second or third year. You
know, it only took a minor flood to put it under. And bear
in mind, this was before Hume Weir was raised and before the dam
on the Mitta [River], "Dartmouth Dam. And there were
a couple more - another dam built on the Ovens River. It was
before all of those, so you could get a flood in the - a minor flood
in the Edwards River at the drop of a hat - the site was very subject
to minor flooding."
The building of the syphon was by no means a new concept at all. They'd
been built before. In fact there were quite a number of - there's
quite a number of small syphons throughout irrigation districts,
tend to be in rather unfrequented spots because they're always
crossing under some water course.
The whole concept of putting irrigation right through this area
was out of ordinary. Not out of the ordinary in the world scale,
but it was bigger but in the same concept as had been done in Victoria
and probably about 10 years ahead of New South Wales, but it was
a copy - not a complete copy, but a copy of what the commission had
already done for the MIA. So, the experience was there.
The main significant feature of the Lawson Syphon was, it was a huge
steel sheet piling job. It was the first time on a large scale
under an active river that we'd attempted to put water under an
active river. There were other much smaller syphons. Probably
the first one that we'd really built was in the Wakool district
where the northern branch canal goes under the Niemur River. But
the Niemur River is normally dry.